BPC has dedicated up to 100 MW of initial surplus power to provide third-party hosting services at favorable target rate, with 3 months of deposit / prepaid hosting fees.

During 2023 BPC constructed and activated its first two data hosting sites for Bitcoin mining. BPC now operates 15 MW of data hosting and manages 4,800 ASIC computers for BTC mining.


By year-end 2023, BPC intends to install and active not less than an additional 50 MW of BTC self mining and data hosting services at new sites under development in West Virginia.

BPC BITCOIN MINING & DATA HOSTING SITES

HZ 10MW
September 22’ | Activated
BR 5MW
January 23’ | Activated
DV 20 MW
March 23’ | Activation
GW 10 MW
May 23’ | Activation
KW 10 MW
July 23’ | Activation
MR 30 MW
October 23’ | Activation